Buck Pool Spinney 2 - footbridge foundations

Foundations for footbridge

Foundations for footbridge over flood drain.

The Environment Agency Constructor Unit laid solid concrete foundations for the bridge beams in September 2001.

Two twelve-meter hardwood beams (from a certificated source) were delivered to the site on 27 Sept 2001.

Environment Agency deliver the bridge beams

The Environment Agency deliver the bridge beams.


1.2 tonnes of beam being towed

Bridge beam being towed.

The beams each weighed 1.2 tonnes and had to be towed across the neighbouring farmer's field.

To save getting a crane to this remote site, the beams were winched across the flood drain, using a tractor and much ingenuity, on 1 October 2001.

Winching beam

Contractor attaching sling to winch beam across flood drain.


Installing deck beams

Contractor about to winch beam across.

The work was hazardous, but success was achieved.

Footbridge decking

 